To add a Start to Finish dependency link, drag the left-side circle from the predecessor towards the end of the successor: To add a Start to Start dependency link, select the predecessor task and drag the left-side circle towards the start of the successor task: To add a Finish to Start dependency link, select the predecessor task (or milestone) and drag the end circle (the one on the right) to the start (left) of the successor task (or milestone): All you need is to drag the little dark blue circles you’ll see when you select a task or milestone: The Timeline view is a simple, visual way to create dependencies between tasks and milestones.